Scheduled Maintenance / Runway Closures At CYOO
NOTAMS will be issued 48 hours in advance of maintenance.
May 21st - late June
A new taxiway joining the hangars to Delta is planned to take a month, starting May 21st.
Wednesday May 29th
Crack sealing is planned which will require both runways to be closed from 07:00-12:00. Temporary closures of taxiways and aprons will occur throughout the entire day.
Week of June 3rd
Line painting is planned for the week of June 3rd and is expected to require two days. Both runways will be closed from 07:00-12:00 on the first day. Temporary closures of taxiways and aprons will occur during the two days selected.